LESCO New Connection: Apply Online
Quick answer: To get a LESCO new connection, apply online on the government ENC portal (enc.com.pk) or through the LESCO website, upload your CNIC, ownership proof and wiring test report, and save the tracking ID. After a site survey you get a demand notice; pay it at a bank and the meter is installed. Track every stage with your ID.
How to apply for a LESCO new connection
- Open the government's online new connection portal (ENC) at enc.com.pk, or the new connection link on the official LESCO website.
- Choose LESCO, your category (domestic, commercial, industrial, agricultural) and the load you need in kW.
- Fill in your details and upload the documents.
- Save the tracking ID. You will need it for every follow-up.
- Wait for the site survey. Staff check the wiring, the nearest pole or transformer and the load.
- Pay the demand notice at a bank when it is issued.
- The meter is installed and a reference number is created. Your first bill follows the next billing cycle.
Lahore region customers can view and print the LESCO duplicate bill with the 14-digit reference number.
Documents you usually need
- CNIC copy of the applicant (owner or occupier).
- Proof of ownership or occupancy: registry, fard, allotment letter, or a rent agreement with the owner's consent.
- Reference number of the nearest neighbour's electricity bill (helps locate the feeder).
- Wiring test report signed by a licensed electrical contractor.
- Recent photographs and an undertaking, if asked by the form.
Exact requirements can differ by category; the portal lists them before you submit.
LESCO new connection fee and demand notice
There is no single fixed fee. The amount on the LESCO demand notice depends on the category, the load (kW), the meter type (single-phase, three-phase or TOU), security deposit and any cost of extending the line or installing a transformer. Homes near an existing pole with spare transformer capacity pay the least.
Pay only the amount on the official demand notice, at a bank. Anyone asking for "speed money" in cash is not an official channel; report it to the company.
Tracking your application
Enter your tracking ID on the ENC portal to see the stage: received, survey, demand notice issued, paid, meter installation. If the application is stuck at one stage for a long time, visit the sub-division with the tracking ID and ask what is pending (often a missing document or a survey visit).
NEPRA rules give companies time limits for each stage. If the company misses them without reason, you can complain to NEPRA.
Notes for LESCO applicants
LESCO receives a very large number of applications in new Lahore housing schemes. In private societies, check first whether the society has LESCO's approval for its electrical network; connections in unapproved schemes are often delayed.
Pick the right load and plan solar early
Add up the appliances you will run at the same time. A normal 5-marla home with one AC usually works on 3–4 kW; homes with several ACs need more. Since the fixed charge depends on your sanctioned load, too high a load costs money every month.
If you plan solar, tell the electrician at wiring time and ask about net metering rules. A solar system with lithium battery installed from day one keeps your first bills low.
How to get a LESCO new connection
- Apply on the ENC portal or company website.
- Upload documents and save the tracking ID.
- Allow the site survey.
- Pay the demand notice at a bank.
- Get the meter installed and receive your reference number.