6 Marla House Construction Cost
Quick answer: a double-storey 6 marla house has about 2,160 sq ft covered area. At standard rates, grey structure costs about Rs 3,092 per sq ft and a complete house about Rs 4,652 per sq ft – so the total is 2,160 × that rate. Use the calculator below for the exact rupee figure and economy or premium options.
| Item | Price | Unit |
|---|---|---|
| Cement (average of PBS north and south) (19 Nov 2026) | Rs 1,576.61 ▼ 14.39 | per 50 kg bag |
| Steel / saria Grade 60 (average) | Rs 263 | per kg |
| Bricks (A class) | — | per 1,000 |
| Grey structure cost (standard, Lahore) | Rs 3,092 | per sq ft covered |
| Complete construction cost (standard, Lahore) | Rs 4,652 | per sq ft covered |
6 Marla house cost: how it is worked out
A 6 marla plot is 1,350 sq ft in a society. A double-storey house on it has about 2,160 sq ft covered area (the calculator default). Cost = covered area × rate per sq ft. At standard quality: grey structure 2,160 × Rs 3,092, complete house 2,160 × Rs 4,652. Economy and premium options are in the calculator.
A 30 ft front on 6 marla allows a separate drawing room; the extra 5 ft width mostly adds wall and slab area, not extra bathrooms.
Single storey vs double storey
| Option | Covered area (approx.) | Notes |
|---|---|---|
| Single storey | 1,242 sq ft | Lower total, higher cost per sq ft (full foundation and roof for one floor) |
| Double storey | 2,160 sq ft | Most common; best value per sq ft |
| Double + roof room | 2,419 sq ft | Adds a room, store or laundry on top |
Main materials needed
| Material | Quantity (approx.) | Today’s rate |
|---|---|---|
| Cement | 907 bags | Rs 1,576.61 per bag |
| Steel (saria) | 8,640 kg | Rs 263 per kg |
| Bricks | 58,300 | see table |
| Sand | 3,888 cft | see table |
| Crush (bajri) | 2,916 cft | see table |
Multiply each quantity by the rate to build your material budget. Rates: cement, steel, bricks.
Where the money goes
| Stage | Typical share of total |
|---|---|
| Excavation and foundation | 8–12% |
| RCC frame, slabs and stairs | 20–25% |
| Brickwork and plaster | 15–20% |
| Electrical and plumbing | 8–12% |
| Flooring, tiles, marble | 10–14% |
| Doors, windows, woodwork | 8–12% |
| Kitchen and bath fittings | 6–10% |
| Paint and polish | 4–6% |
Shares are typical for a standard-finish house and vary with design and finishes.
Finishing choices that change the total
In a 6 marla house, kitchens and bathrooms take the largest share of finishing money. Standard sizes and fittings keep costs in check.
- Flooring: local tiles vs marble vs imported porcelain
- Kitchen: basic cabinets vs modular kitchen with granite top
- Bathrooms: local vs imported fittings
- Doors and windows: solid wood vs ready-made, aluminium vs uPVC
- Ceilings: plain plaster vs false ceiling with lights
Time needed
With funds and materials ready, a 6 marla double-storey house typically takes about 8–10 months from excavation to handover: roughly 40% of the time for grey structure and 60% for finishing. Delays usually come from changing the design mid-way, slow payments and material shortages.
Tips to control 6 marla building cost
- Get the naqsha approved and a structural design made before starting.
- Agree a written scope with the contractor and pay in stages.
- Lock steel and cement purchases when rates are stable.
- Pick finishes early; keep 10% contingency.
- Plan solar, ACs and insulation now – see the store box for solar systems and ACs.
- Check land facts on the 6 marla plot size page.